Generator Fuel line installation in Hythe, Kent

Generator Installations were asked to supply and install 3/4” feed and return pipe work for a major supermarket chain in Hythe, consisting of 10 meters of pipe and 6 bends per line from the bulk tank to the generator set engine hoses.

All pipe work was pressure tested to 1.5x working pressure to ensure the connections were secure and would not leak. On completion all pipe work was painted to denote oil.