London Generator Project coolant and fuel system install

Generator Installations were asked to install a full generatro cooland and fuel system installation at a large commercial development in London

IMG_0690 IMG_0653

IMG_0669

The specification called for a complete the coolant system of 400m of 3″ coolant lines, 200m fuel system. including; 25mm in 50mm pipe in pipe transfer lines, 100mm single skin welded vent lines, 50mm single skin screwed fill lines, pump sets and fuel polisher. Much of the pipe work was installed in confined spaces and in a vertical riser to the roof adding to the challenge of an already large job.

This wide range of specifications was no problem for Generator Installations highly experienced team of engineers and installers