Large Residential Complex, Central London – Mild Steel Pipework & Electrical Installation

We have recently started the following works on a large residential complex in Central London

Fuel System

  • Complete fuel system works consisting of double and single skin flanged and fully welded pipework
  • Fuel polisher system
  • Pump set
  • Fire valve
  • Fill point cabnet

Coolant Pipework

  • Fabrication and installation of 75 meters of flanged welded mild steel pipework to connect generator set located in sub basement to remote radiator located on the roof eleven stories above.

Exhaust

  • Installation
  • Fabrication and installation of interconnecting flue between generator and silencer
  • Insulation of flue for safety and ...
Continue Reading →
0

Internation bank, Central London – 2 x 2500kVA Generator Installation

Generator Installations have recently been commissioned to complete the following works for an international bank located in central London.

Offload and position 2 x 2500kVA generators
Contract lift remote radiators onto roof
Offload and position fuel tanks
Installation of
• 400m of 150mm coolant pipework
• 200m of pipe in pipe mild steel pipework
• Fuel system ancillaries
• Bund around each generator
• 2 primary and secondary exhaust silencers and interconnecting flues and downpipes to engine bellows
• Insulation of ...

Continue Reading →
0

Data Centre in Nottingham – New Fuel System Installation

We have recently completed a major fuel system upgrade for a data center based in Nottinghamshire.

Works completed included:

• Decommission, clean, degas, remove and dispose existing 68,000Liter bulk tank and existing single skin fuel pipework
• Installation of 2 x new 20,000Liter Double Skin Bulk Tank
• Installation of 70m of pipe in pipe common flow and return lines to 3 containerised generators
• Fuel System Electrical Installation

Continue Reading →
0

Blue Chip Bank in London – 2 x 800kVA Generator Installation

This week we completed the installation of 2 x 800kVA generators for a UK bank HQ in London, Offload was required to be offloaded down a void of 30m into the basement and skated into plant room. Cleaned & De-gased an existing 100,000Litre bulk tank. Installed a new fuel system including pipe in pipe mild steel pipework and 2 new day tanks, fuel polisher, all associated control cables, installation of pump panel and bund alarms and steel bund around the ...

Continue Reading →
0

Generator plant room installation for a new office block development in central London

GI have been commissioned to install a new generator plant room fit out for a new development in central London, the install consists of offload and position, coolant pipework from the generator located in the basement to the radiator located on the roof of the building, fuel system, including pipe in pipe mild steel pipework and commission the installation. Last week we completed the offload and position.Generator silencer Continue Reading →