Generator Installation in Central London

New generator and fuel tanks ready to be installed, for a major blue chip company in central London. The job consists of two generators to be offloaded and positioned in the basement of the building next week.

We have been commissioned to offload & position the set, supply and install the fuel system, install primary and secondary silencers and complete all electrical works. Watch this space for more news on this project in the near future.

Continue Reading →
0

Data Centre UPS Installation in Birmingham

Last week we completed a UPS Installation for a large data centre in Birmingham. We had to terminate and remove he old sets which included UPS systems, redundant 2400KG transformers out of confined space canopy. Then install 3 new UPS systems, 150 new batteries and all of the associated cabling. Please see some pictures of the works undertaken below.

Continue Reading →

0

Heathrow Airport Generators Installation

Generator Installations have just completed installing 3 x 2000Kva Generator sets at Heathrow Airport. The works consisted of fitting out the mechanical and electrical works within the container of each generator. Installing over 4500m of 630mm cables. 90m of pipe in pipe fuel line and all necessary mechanical works to complete the installation.

Continue Reading →
0

Data Centre UPS Installation

Last week we completed a UPS Installation for a large data centre in Birmingham. We had to terminate and remove he old sets which included UPS systems, redundant 2400KG transformers out of confined space canopy. Then install 3 new UPS systems, 150 new batteries and all of the associated cabling. Please see some pictures of the works undertaken below.

Continue Reading →
0

Offload & Position Generator and ancillaries for a new development in central London.

As previously mention we have been commissioned to install a 1200Kva Generator Set and Fuel System in a new development in London.

Last week we completed the offload & position of the set. We used a tower crane to lift the set from a flatbed lorry and lowered the generator to the basement level with only a few centimetres of free space either side. The set was placed onto an offload stand and was lowered and skated to its final ...

Continue Reading →
0

Fuel system installation for a hospital in the south of England

This week Generator Installations have just completed an installation of a generator fuel system for a hospital in the south of England.

Generator Installations was commissioned to supply and install a fuel point cabinet complete with hydrostatic contents gauge and overfill alarm, connected to an 18000Litre double skin bulk tank, along with a UPP polyethylene pipe in pipe between the bulk tank and the generator set canopy. All pipework was pressured tested to twice the working pressure.

Continue Reading →
0