Generator Installations were asked to carry out a machine movement in Warwick. The job included moving an existing 60kVA generator 600 meters from its current location into a new purpose built compound, taking delivery of a new bulk fuel tank and supplying and installing a fuel transfer system between the bulk tank and the generator base tank.
Our experienced plant movement engineers moved the generator quickly and safely, while protecting a newly laid footpath from the weight of the generator.
Once the generator was positioned and the fuel system was installed the set was fully commissioned and run for 30 minutes.
During the works we supplied a temporary generator to ensure the clients DRP was not compromised.