Generator Fuel line installation in Hythe, Kent

Generator Installations were asked to supply and install 3/4” feed and return pipe work for a major supermarket chain in Hythe, consisting of 10 meters of pipe and 6 bends per line from the bulk tank to the generator set engine hoses.

All pipe work was pressure tested to 1.5x working pressure to ensure the connections were secure and would not leak. On completion all pipe work was painted to denote oil.

IMG_0614 Continue Reading →

0

Plant movement and installation in Warwick

Generator Installations were asked to carry out a machine movement in Warwick. The job included moving an existing 60kVA generator 600 meters from its current location into a new purpose built compound, taking delivery of a new bulk fuel tank and supplying and installing a fuel transfer system between the bulk tank and the generator base tank.

IMG_0714

Our experienced plant movement ...

Continue Reading →
0