Fuel System Installation

23

Generator Installations were tasked with installing an 8000 litre fuel tank into the basement of an existing, occupied development. Initially we was asked to complete a site build 8000 litre double skin fuel tank as access was very limited at site, however after a survey Generator Installations designed an innovative solution, installing four, smaller tanks equalling 8000 litre capacity, balanced through a sealed ...

Continue Reading →
0

Fuel Pipework Pipe in Pipe jacked double skin bunded pipework

Fuel systems must be protected against leaks that can cause severe environmental damage. Due to building regulations fully welded ‘pipe in pipe’ systems are common place in many installations, wherever fuel must be transported through a building and no bunding is present. Pipe in Pipe solves this problem without the need for any structural or cosmetic alterations to the existing building. The inner pipe acts as the channel in which the fuel will flow and the larger, outer pipe, acts a ...

Continue Reading →
0

Friends of Wisdom Hospice Charity Fund Raising Event

Generator Installations helped raise an incredible £5,614.53 for the Friends of Wisdom Hospice. The money was raised at a fund raising event in memory of Stuart China, the father of company director Richard China.

The hospice have advised the money will pay the salary of a specialist palliative care nurse for 3 months.

A special thanks to Emma Martin for managing the fund raising event.

Below is a photo of the cheque being handed over to the Hospice who was extremely grateful.

Continue Reading →

0

Generator Installation in Bath

Generator Installations wasasked to carry out a generator and fuel system installation in Bath. Generator Installations provided a bespoke installation of the generator, acoustic attenuation, exhaust silencer and fuel system.

All of the pipe work and silencer supports wasdesigned and custom made off site to ensure quick and easy installation, minimising any possible site down time.

Bath 2

The fully designed and installed fuel system includes a bulk fuel storage tank with level ...

Continue Reading →
0

London Generator Project coolant and fuel system install

Generator Installations were asked to install a full generatro cooland and fuel system installation at a large commercial development in London

IMG_0690 IMG_0653

IMG_0669

The specification called for a complete the coolant system of 400m of 3″ coolant lines, 200m fuel system. including; 25mm in 50mm pipe in pipe transfer lines, 100mm single skin welded vent lines, ...

Continue Reading →
0

Generator Installation in Greenwich

Generator Installations have installed a generator at a large residential development in London.
The specification called for a full installation starting with installing an enclosure on the generator. The next task was to install a fill point cabinet in a suitable location and make all connections between the cabinet and the generator, including pipe in pipe fuel lines and power and control cables and a bespoke fuel system panel and breaker.

IMG_0957

Continue Reading →
0

Generator Fuel line installation in Hythe, Kent

Generator Installations were asked to supply and install 3/4” feed and return pipe work for a major supermarket chain in Hythe, consisting of 10 meters of pipe and 6 bends per line from the bulk tank to the generator set engine hoses.

All pipe work was pressure tested to 1.5x working pressure to ensure the connections were secure and would not leak. On completion all pipe work was painted to denote oil.

IMG_0614

Continue Reading →
0

Double skinned tank install in Milton Keynes

Generator Installations were asked to supply and install a 2500 litre double skinned fuel tank for a large retail distribution centre in Milton Keynes. The tank was delivered with intergral fill point, gauges and overfill alarm.

IMG_1337 IMG_1339

Once the tank was offloaded and positioned, connections had to be made between the tank and the generator containers, this was achieved using a ...

Continue Reading →
0

Three 2500kVA generators installed at a data centre in slough

Generator Installations was asked to assist with the installation of three 2500kVA generators at a large new build data centre in Slough. This job presented a unique set of challenges that our team of experienced engineers and lift supervisors handled quickly, cost effectively and safely.

The first challenge, how to get three 15 ton diesel tanks into an already part constructed building on offload conditions, where the space was limited to 10mm allowance?

IMG_3958

The solution, ...

Continue Reading →
0
Page 1 of 6 12345...»